1x16MW Lignite Fired Power Plant Project, Nigeria

Owner: Lafarge Africa plc

Location: Ashaka Cement, Gombe, Gombe State, Nigeria

Fuel: Lignite (Maiganga coal mine in Gombe State)

Features:

COAL FIRED POWER PLANT: the first coal fired power plant in Nigeria in the last few decades

ISLAND MODE OPERATION: reliable and continuous operation

AIR COOLED CONDENSER: save water

CONSTRUCTION PERIOD: 21 months

EXECUTION STANDARDS:

1. Design: ISO and American standards;

2. HSE: Nigerian and Lafarge standards;

3. Environmental: IFC and Nigerian standards;

4. Equipment: ISO standards;

5. Boiler and pressure parts: ASME;

6. Fire-fighting: NFPA and Nigerian standards.